Rotary Park Update (9/10/15)

Phase 1 Construction of playground, kayak launch, fishing bridge and infrastructure for restrooms.

Progress: Rotary Park is nearing the construction phase of the grants execution.  Hooker DeJong completed post bid conferences for the bid proposals submitted for construction of Rotary Park.  After review of bids, the DNR negotiated an amendment to the current award  to include the handicap accessible kayak launch. With the amendment, the County Board approved resolution to amend the DNR grant contact, as well as support the parks phase one completion with the remaining 130,000 necessary to complete phase 1.

The Board also approved award of the construction contract to Muskegon Quality Builders, project leaders anticipate construction to begin by the end of September 2015. The grand opening for the park will be targeted for Spring of 2016.